Bikeway Network – 2011 Update 1st consideration June 23 2011

 

This item will be considered by Public Works and Infrastructure Committee on June 23, 2011. It will be considered by City Council on July 12, 2011, subject to the actions of the Public Works and Infrastructure Committee.

The Acting General Manager, Transportation Services, recommends that:

 

1.         City Council endorse the direction and implementation of the Mayor’s Bike Plan comprising a 100 km network of off-street bike trails and completion of critical on-street bike lane connections where the community supports them….

and where they do not impede traffic flow.

 

two areas where  they are in consideration in the greater wards 11,12,13,14 and greater Junction are…

 

3.         City Council approve modifications to the bicycle lanes on Dupont Street at the approach to the intersection with Lansdowne Avenue, to move the beginning of bicycle lanes from a point 30 metres east of Lansdowne Avenue to a point 70 metres west of Lansdowne Avenue.

 

4.         City Council provide direction regarding the installation of approved bicycle lanes on Bloor Street West, from Mill Road to Beamish Drive.

full report PDF link Bikeway Network – 2011 Update.pdf

 

Background Information
(June 9, 2011) Report and Appendices 1 to 7 from the Acting General Manager, Transportation Services, on Bikeway Network – 2011 Update
(http://www.toronto.ca/legdocs/mmis/2011/pw/bgrd/backgroundfile-38906.pdf)


Source: Toronto City Clerk at www.toronto.ca/council via Sarah Doucette @DoucetteWard13

 

 